Procedure for Changes to Registered Project

Revalidation Process

          In the case of a registered project requiring revalidation, the project participants shall revise the Project DesignDocument (PDD) according to the actual implementation.  The revised PDD shall be validated by a Validation and Verification Body (VVB) following the Guidelines for Validation and Verification of Thailand Voluntary Emission Reduction Program .  

Change that required revalidation is a change that affect the amount of GHG emission reductions including;

-  Addition of project activity/methodology.

-  Increase of the amount of GHG emission reductions to more than 60,000 tCO2eq/y or the increase compared to the expected GHG emission reductions stated in the registered Project Design Document (PDD) is more than 15%. 

 

 